GC000500T140 page 3 Economic assumptions • Real discount rate (weighted average cost of capital) of 2.6% can be used for NPV analysis • High level generation technology installed cost component assumptions: Sensitivity scenario Low High Solar installation - fixed project costs (civil, connection, network augmentation, protection, control integration etc) $500,000 $1,000,000 Solar installation – variable per kW of solar capacity installed $1500 / kW $3000 / kW Operational cost for the solar farm $10,000 per year $25,000 per year Wind installation – fixed costs (civils, approvals, connection, control, integration) $1,000,000 $2,000,000 Wind installation – variable per kW of wind capacity installed $1,000 / kW $3,000 / kW Operational cost – wind installation $20,000 per year $50,000 per year Energy storage – fixed project costs $500,000 $900,000 Energy storage – cost per kWh installed $600 / kWh $900 / kWh Operational cost for the energy storage $15,000 per year $25,000 per year